|
Monthly Newsletter Left Menu
|
Alyeska
work crews reconfigure Pump Station 12
Alyeska recently took one of the TAPS pump stations permanently
out of pumping operations because the station was no longer needed
to accommodate changing pipeline throughput demands from North
Slope production. Some buildings and other physical infrastructure
at Pump Station 12 (PS 12) were removed. During a pipeline
shutdown on July 23-24, work crews installed a straight pipe
bypass, isolating the station. The pumping purpose of the station
is being retired and PS 12 will serve as a "flow-through" station.
It will only be used to support cold restart - should that be
necessary - which would require additional equipment and keeping a
relief tank on site.

During the original construction of Trans Alaska Pipeline System
(TAPS), PS 12 was constructed to help move oil at flow rates over
1.2 million barrels per day. The station is approximately 65 miles
north of Valdez near the communities of Glennallen, Kenny Lake and
the Greater Copper River Valley.
TAPS was originally designed to have 12 pump stations, but only 11
were built due to overall pumping efficiency and the development
of drag reduction additive (a chemical additive that makes oil
flow through the pipeline more easily by reducing turbulence
within the oil flow and friction between the crude oil and pipe
wall). Although pump station numbers run from 1 to 12, PS 11 was
never operational. PS 5 is a pressure relief station on the south
side of the Brooks Range which has no main line pumps.
Alyeska plans to install electrically driven oil pumps at Pump
Stations 1, 3, 4 and 9 as part of its pipeline modernization
project, known as Strategic Reconfiguration. The goal of the plan
is to simplify operations and increase Alyeska's ability to more
efficiently accommodate changing pipeline throughput demands.
|
 |