|
Monthly Newsletter Left Menu
|
Pipeline integrity study improves inspection process
Alyeska engineers have devised a better way
to find hidden dents and other mechanical damage to the Trans
Alaska Pipeline System (TAPS).
They developed a technique to review data collected by an
ultrasonic in-line inspection tool, better known as a "pig," to
efficiently discover and examine the extent of mechanical damage
to pipeline walls. The technique improves TAPS safety and
efficiency by allowing engineers to determine if damage is
significant and in need of repair without having to dismantle or
excavate sections of pipeline for visual inspection.
"Our
engineers analyzed the ultrasonic pig data from 2001, which
revealed small dents in the pipeline," said Janna Miller, Alyeska
system engineering supervisor. "Nobody in the industry had ever
used an ultrasonic pig to look at data this way."
Engineers identified 77 belowground pipeline sections as having
possible mechanical damage and requiring visual inspection. Crews
excavated about 40 of these sites between 2001 and 2004 to inspect
and repair damage and to better understand the scanning data.
Engineers now believe the remaining sites probably have very small
dents that pose no significant threat to pipeline integrity, but
they are still assessing the sites to be certain.
"After analyzing the data from the digs, we determined that it
might not be necessary to complete the remaining digs but there
was no method or industry guidelines that suggested we wouldn't
have to do this work," said Miller.
The project team that worked on this pipeline integrity study
included Alyeska engineers Elden Johnson, Alan Beckett and Bhaskar
Neogi. They completed an extensive engineering assessment,
conducted sensitivity analyses of the data and used a risk
management analysis to determine which sites should be inspected.
Their analysis determined that 29 of the remaining 35 dents do not
require excavation. This determination avoided substantial costs
and eliminated risks associated with digging up the mainline pipe
29 times. Miller said six of the remaining locations are still
being studied.
"Pipeline inspection can be very expensive, especially when
excavation is required," said Miller. "A lot of equipment and
personnel are needed to complete this complex and often hazardous
type of work."
Alyeska uses three types of pigs to inspect and maintain the
pipeline. Cleaning pigs are sent through the pipeline every week
or two to scrape wax buildup off the pipe walls. Corrosion pigs
are used every three years to scan the pipeline with either
ultrasonic or magnetic flux leakage detection devices to monitor
corrosion and evaluate pipeline integrity with respect to
corrosion damage. And operators use geometry pigs every five years
or when needed to evaluate the stresses in the pipe and to check
for bending in the pipe wall by measuring the bending radius and
pipe ovality.
|
 |