|
Monthly Newsletter Left Menu
|
In the
Field
Pump Station 1 connected to Prudhoe Bay power grid
Alyeska reached a pipeline reconfiguration
milestone this spring when workers connected Pump Station 1 (PS 1)
to Prudhoe Bay's central power grid.
PS
1 will use as much as 21 megawatts (MW) of electricity during
normal operation after electrification is complete: enough power
to serve 7,000 homes. It will use two new gas turbine generators
to produce up to 18 MW of electricity onsite. Prudhoe Bay's
central power station will provide additional electricity and
could supply all of PS 1's power if needed. Workers started this
power grid tie-in last winter by building an ice road and drilling
and installing power poles that now carry 2,500 feet of overhead,
69-kilovolt power line. They also trenched and laid 1,100 feet of
three-phase insulated cables beneath existing pipelines and roads.
Project managers expect to terminate the tie line at a substation
so that commercial power can be turned on later this fall. All of
the pipeline's currently operating pump stations will be fully
electrified after pipeline reconfiguration.
Following
pipeline reconfiguration, PS 3 and PS 4 will generate all power
onsite and PS 09 will receive commercial power from Golden Valley
Electric Association via another substation to be installed this
fall.
The 800-mile-long trans-Alaska pipeline currently transports
nearly one million barrels of crude oil per day from Prudhoe Bay
to the port of Valdez. Pump Stations 1, 3, 4, 5 and 9 will be
upgraded and standardized with equipment and new
electric-motor-driven pumps. Pump Station 5 will not require a new
pump module but will be upgraded to function as a relief station
on the lower side of Atigun Pass.
|
 |