Monthly Newsletter Left Menu
|
The New
TAPS
A closer look at Strategic Reconfiguration
At
the core of Alyeska’s Strategic Reconfiguration project are the
new electrically driven pumps being installed at Pump Stations 1,
3, 4 and 9. These stations will have three pump modules, each
comprising an electric motor, a crude oil pump, a lubrication oil
skid that supplies lube oil to the crude pump and motor and a sump
tank to collect potential oil leakage. The modules will replace
the existing turbine engine-driven pumps that have moved oil
through TAPS since startup in 1977. When pump station upgrades are
complete, TAPS will be able to pump up to 1.14 million barrels
daily and to more readily make adjustments to changing flow
forecasts.
|
 |