|
Monthly Newsletter Left Menu
|
Refrigerating the Pipeline
For almost every inch of the 800-mile pipeline, design engineers
who designed and built this system faced a different
environmental challenge. There were more than 800 river and
stream crossings. The migration of indigenous animals could not
be interfered with. The pipeline had to traverse three mountain
ranges. And for most of the year, construction was taking place
in one of the harshest climates on earth.
One of the more daunting challenges was figuring out a way to
avoid burying the line in areas dominated by permafrost, where
the ground is permanently frozen, and the warm crude oil posed a
risk to frozen soil and pipeline stability. To avoid this, 420
miles was elevated above the surface of the ground. For three
segments—totaling about four miles—this was not possible and
these sections had to be buried in the permafrost to accommodate
caribou migrations and road crossings. One of the sections,
located at Milepost 647, is about two miles long. The other
sections are located at Mileposts 652 and 684, and are each
about one mile long.
The solution? Cooling systems were installed to keep the
permafrost from thawing. In these areas, the pipe is insulated
with three inches of polyurethane foam covered with a
resin-reinforced fiberglass jacket. Pipes adjacent to the
mainline carry refrigerated brine to keep the surrounding soil
frozen.
To maintain pipeline integrity and protect the environment,
Alyeska monitors the pipeline, including its belowground
sections, with “smart pigs”—inspection gauges that run inside
the pipeline and to aid in identifying any anomalies, using
ultrasonic, high-resolution imaging.
In 2004, a Magnetic Flux Leakage (MFL) corrosion pig was sent
through the pipeline. This state-of-the-art pig uses a magnet
and sensor to record pipe wall thickness. After analyzing data
from this pig run, Alyeska identified locations where wall loss
had occurred around some girth welds in heat-affected zones and
along the axis where insulation pieces meet and the original
pipe coating had failed. Where necessary, repairs will be made
by installing reinforcement sleeves.
After the sleeves are installed, a quality check will be
performed to verify that the welds meet Alyeska standards. Under
the sleeves, areas of corrosion-related wall loss will also be
filled with putty or an epoxy. Monitoring rods will be mounted
on the top of the sleeves to check for settling of the pipe
after the repair sites have been backfilled.
|
 |