|
Monthly Newsletter Left Menu
|
In the
Field
Valves Focus of 2006 Pipeline Maintenance Shutdown
During last summer's scheduled pipeline shutdown, Alyeska
discovered that Check Valve 109 (CV109) did not meet internal
performance standards. A risk assessment was conducted and it
was determined that the valve—located in an environmentally
sensitive area south of Glennallen—should be replaced.
The 2006 maintenance shutdown started at 6 a.m. on Saturday,
July 22, and the pipeline was restarted at 1:32 p.m. the
following day. Although the maintenance was scheduled to last 36
hours, most of the work was completed 4.5 hours ahead of
schedule.
“That we were able to finish ahead of our anticipated restart
goal is a direct result of their focus on safety and excellent
pre-planning,” Jim F. Johnson, Pipeline Vice President said.
Work crews spent many weeks preparing for the maintenance and
repair project. Over 100 TAPS employees were involved in
replacing CV109. At the same time, additional crew completed
other
maintenance
projects along the pipeline, including the installation of a
check valve at Pump Station 10. CV 109 is one of 82 check valves
located along the 800-mile-long pipeline. The valves are
designed to be held open by flowing oil and to close
automatically when oil flow stops or is reversed.
“The credit really goes out to everyone working in the field, at
the terminal, and throughout the company who helped plan and
execute the work,” Johnson added.
Installing the check valve at Pump Station 10 included a
procedure known as "hot tapping": drilling a hole into the
pipeline through a split-tee to provide access points for
stopple installation. The pipeline was sealed by inserting
stopples into the 48-inch diameter pipeline through the hot tap
on each side of the valve, plugging and isolating the pipeline
both upstream and downstream of the check valve.
|
 |