Monthly Newsletter Left Menu
|
The New
TAPS
Electric Pump Station to come online
Due to the remoteness of TAPS, most pump stations must generate
their own electrical power. This is currently accomplished with
aging, skid-mounted turbine generator packages that require
ongoing maintenance. As part of Strategic Reconfiguration (SR),
four pump stations will become electrically driven. PS 1 and PS
9 will tie into commercial utility grids. Pump Stations 1, 3,
and 4 will generate their own electrical power using modern
skid-mounted turbine generators. PS 7 will not be modified at
this time.
PS 1, PS 3 and PS 4 currently use natural gas for general fuel
needs such as mainline pump drivers, power generation and
facility heating. Following SR, fuel gas will be used for backup
power generation at PS 1 and primary power generation at PS 3
and PS 4.
|
 |