|
Monthly Newsletter Left Menu
|
President's Message
Kevin Hostler, President and CEO
Progress continues on Strategic
Reconfiguration project

Alyeska continues to make major changes to the
Trans Alaska Pipeline System’s (TAPS) pump stations through our
Strategic Reconfiguration Project, one of the most significant
investments since construction of the pipeline. TAPS was
originally designed for twice the current throughput and has
operated for nearly 30 years using on-site personnel to monitor
pipeline operations. Installation of electrically driven pumps
at four critical Pump Stations (PS) 1, 3, 4 and 9, along with
modern automation and control equipment, will allow the stations
to be operated remotely, like pipelines throughout the Lower 48.
The design also provides the flexibility to adjust for future
increases and decreases in crude oil flow throughputs.
The reconfiguration is expected to lower overall operating costs
by approximately 10 percent annually and eliminate maintenance
costs for equipment at as many as 75 facilities that will be put
in non-operational status. Minimizing the cost of operation
extends the economic life of TAPS and North Slope oil fields.
Visits to the field and conversations with the pipeline
reconfiguration team led to a decision to alter the
reconfiguration implementation plan and focus on the completion
of PS 9, then move to PS 3. Once PS 3 and 9 are complete, we
will shift resources to PS 1 and 4.
A variety of factors led to this decision, among them were the
continued challenges around incomplete or late design
engineering, issues with turbine generators, and resource
constraints. Late design engineering had a two-fold impact on
the project schedule and cost: the incomplete design scope made
it difficult to accurately plan field work and complete
procurement; and design changes after mobilization of field
contractors resulted in increased costs.
Additionally, it became apparent that some of our internal
resources were becoming overcommitted. Simplifying our approach
by completing two stations at a time corrects this problem. This
also resolves bed space issues at all the pump stations.
This strategic and historic investment in the pipeline is an
investment in Alaska’s oil industry that will pay dividends for
years to come.
|
 |