|
Monthly Newsletter Left Menu
|
Pipeline
upgrade project focuses on startup of Pump Station 3 and moving
Pump Station 9 off legacy equipment
Alyeska crews are now working to upgrade Pump Station 3 as part
of Strategic Reconfiguration (SR). A decision was made in 2006 to
undertake a phased startup of the pump stations. Pump Station 9,
near the interior town of Delta Junction, was the first station
to bring the new pumping equipment and control systems on line,
in part because of its proximity to commercial power.
“We changed our approach to help the SR crews get the processes
right before implementing the technology,” said John Plenger, SR
Program Manager. “This phased approach also ensures work crews
are able to take lessons learned to the remaining stations.”
Now, as work at PS 9, shown below, nears completion, crews have
resumed SR work at PS 3, located north of the Brooks Range and
Atigun Pass. SR construction work at PS 3 was nearing completion
when work at the station was suspended in 2006. The project at
PS 3 now focuses on completing construction, then moving on to
functional checkout and commissioning.
Functional checkout involves a detailed process of checking all
of the equipment and devices to ensure they work properly and
are communicating with the control systems.
Commissioning will take this one step further to ensure the
functional systems operate as designed, and prepare all
documentation for handover to the team that will start up the
station.
Under the SR project, Alyeska is installing electrically-driven
pumping equipment at Pump Stations 1, 3, 4 and 9. Originally
crews spent more than two years working simultaneously at each
of the four pump stations, with the goal to complete the
reconfigurations and put the new systems online all at once.
SR is a significant project for Alyeska’s overhaul of the
pipeline that will modernize operations and allows for
automation from the Operations Control Center, which will soon
be moved from Valdez to Anchorage.

|
 |