|
Monthly Newsletter Left Menu
|
Pipeline Restarted After
Leak on Bypass Piping Stopped
The source of a leak at Remote Gate Valve (RGV) 32 has been
identified as a loose fitting on a valve on a secondary piece of
piping that bypasses RGV 32.
A baseline maintenance coordinator was conducting routine
inspections just south of Atigun Pass and discovered the leak at
approximately 8:20 a.m., Tuesday, January 9, 2007. The pipeline
was shutdown at 8:35 a.m.
Alyeska
immediately activated a response team near the site and an
Incident Management Team in Fairbanks to manage the situation
with the objectives to stop the leak, initiate cleanup efforts,
and determine necessary repairs for a pipeline restart.
Once the source of the leak was identified, the fitting was
quickly tightened and the leak stopped. Both sides of the
secondary piping were isolated from the pipeline and crews
tested the pressure requirements of the valve and determined it
fit for normal operations. Meeting these requirements allowed
Alyeska to begin normal operations and the pipeline was fully
restarted January 9th at approximately 3:00 p.m. – about 6 hours
after it was shut down.
Once the leak had been stopped, the primary focus turned to oil
recovery and cleanup.
There were approximately 800 gallons of oil on the right-of-way
gravel work pad, covering about a 25-foot radius. The oil was
confined to the work pad. The extreme cold, ranging from 33 to
44 degrees below zero (Fahrenheit) helped minimize the
environmental impact by turning the spilled oil to gel and
limiting the spill area.
Throughout the day, oil spill response personnel worked with
equipment, including a vacuum truck and hand tools, to recover
and remove the spilled oil. The responders were able to pick up
all oiled snow and free liquids at the site within 48 hours of
spill discovery. The response followed a controlled, systematic
approach to ensure personnel safety. While weather conditions
aided in mitigating the environmental damage of the spill, the
cold temperatures presented difficult working conditions for
those in the field.
Following the removal of the oil and contaminated snow and
gravel, the recovered product was transferred to Pump Station 5
where it underwent a separation process so that it could be
metered and injected into the pipeline.
“Our goal is to have zero spills but we must be prepared for
every situation,” said Jim F. Johnson, Pipeline Vice President.
“Alyeska conducts pipeline spill response exercises throughout
the year to train responders, field test equipment and improve
our response techniques for situations like this.”
|
 |