|
Monthly Newsletter Left Menu
|
In the
Field
Reconfigured pumps at PS 9 reach one-year milestone
It
has been over a year since Alyeska started moving oil at Pump
Station 9 with the new equipment installed as part of Strategic
Reconfiguration (SR). The SR project involves installing
electrically driven crude oil pumps at four critical pump
stations (1, 3, 4 and 9) combined with increased automation and
upgraded control systems. PS 9 was the first station to receive
new equipment.
Original plans called for all four pump stations to be
reconfigured at once. Crews spent more than two years working
simultaneously at each of the four pump stations, with the goal
to complete the reconfigurations and put the new systems online
all at once.
“When we moved to a phased implementation of SR at the pump
stations, we decided to first start with PS 9,” said Jim F.
Johnson, Pipeline vice president. “It was the most accessible of
the pump stations, and its proximity to the commercial power
grid meant that we did not have to install onsite power
generation.” PS 9 uses electricity for the new equipment via
commercial power from Golden Valley Electric Association (GVEA).
The power source at PS 3 and PS 4 will be provided by two new
turbine generators located at each station.
“We learned a great deal from working with the new systems and
pumps at PS 9, and we were able to take lessons learned and
successfully apply them to our subsequent work at PS 3,” said
Johnson. “This is a challenging project—the most significant on
TAPS since pipeline construction. We continue to deal with and
work through challenges as they arise, even if it means slowing
the pace at times.”
During this past year, the SR pumps at PS 9 have proved to be
highly reliable. The commercial power provided by GVEA has also
been reliable, meeting company requirements.
|
 |