|
News Bulletin 1397
Alyeska Pipeline Service Company Starts Up
New Pumps at Pump Station 9
First station switches to modular, scalable equipment
ANCHORAGE, AK
- Alyeska Pipeline Service Company reached
a significant milestone over the last several days in its
efforts to upgrade and modernize equipment with the start up of
the electrified pumps at Pump Station 9, located just south of
Delta Junction.
Oil first flowed
through the newly installed equipment at about 4:30 last Friday
evening
and began using the new
pumps on a continuous basis today.
Alyeska
alternated the pumping of oil using its "legacy", or existing,
equipment and then switching to the newly installed electrified
pumps through the weekend. The legacy pumps were the same style of
pumps that have been in place since the Trans Alaska Pipeline
System's (TAPS) original startup in 1977. Alternating between the
new and the legacy equipment gave technicians and engineers an
opportunity to test the new system in several different ways. While
work at Pump Station 9 still remains before Alyeska declares a
complete startup of the operations, the testing phase is essential
in providing assurance that the system meets the company's needs.
This is a
significant step in Alyeska’s measured, phased approach to complete
the modernization of Pump Station 9. Alyeska crews will closely
monitor the equipment operations and make necessary adjustments as
warranted over the next 30-45 days.
The Pump Station
9 work is part of a project Alyeska calls Strategic Reconfiguration.
This project is a significant upgrade to the pipeline's pump
stations and control system using modern technology and processes.
The project involves installing electrically driven crude oil pumps
at four critical pump stations combined with increased automation
and upgraded control systems.
In addition to
being more efficient, the new equipment uses modern pollution
control technology. Additional environmental improvements will
include reduced domestic and industrial waste generation, and a
lower risk of spills due to the reduction in requirements for liquid
turbine fuel delivered by truck.
This will
position TAPS for more efficient operation while maintaining or
enhancing safety, operational integrity and environmental
performance. The new system, which is modular and scalable, will
also provide more flexibility for future increases or decreases in
throughput.
Once Alyeska
officials are satisfied with Pump Station 9’s performance, crews
will turn their attention to reconfiguring Pump Station 3. Alyeska
engineers will apply the lessons learned from the Pump Station 9
project to help with the completion and startup of Pump Station 3. Alyeska
will then focus attention on making upgrades to Pump Stations 4 and
1 respectively.
“Our focus has
been on the safe, quality startup of Pump Station 9,” said Kevin
Hostler, Alyeska President and CEO. “We will learn from this as we
move our resources to Pump Station 3. While this is an exciting
time for us, there is still work to get done on this project.”
Hostler further
noted that Strategic Reconfiguration may be the largest project
Alyeska has undertaken since the original construction of the
pipeline.
“We have a lot
of work to do before all upgrades at the pump stations are complete
and I am extremely proud of the hard working men and women who have
put in a lot of extra hours to upgrade this station,” Hostler said.
“I also want to acknowledge the team that got us to this point and
this includes our contract workforce.”
Pipeline Vice
President Jim F. Johnson is not only proud of the work performed on
Pump Station 9, he is also pleased with the processes Alyeska put in
place to ensure employee concerns regarding the project were
received, evaluated and addressed appropriately. "We pride
ourselves on our open work environment that allows employees and
contractors to voice their concerns about any phase of a project or
work activity. We are very satisfied with how the work has
progressed at the site and we thank all involved for their
commitment to deliver the project safely."
There were three
major contractors responsible for the implementation work at Pump
Station 9. ASRC Energy Services Pipeline, Power and Communications
(PPC) installed the modules and all of the piping, electrical and
communications equipment and systems; Kakivik Asset Management
performed the required inspections; and Udelhoven Oilfield System
Services completed the functional checkout of each component and
system. These implementation activities were followed by Alyeska
Commissioning and Start-up teams, who successfully brought the
station on line. All of the work associated with Strategic
Reconfiguration has been closely coordinated and monitored by state
and federal regulating agencies including the Alaska Department of
Environmental Conservation, Department of Transportation, and the
Joint Pipeline Office.
More than 15 billion barrels have moved through the
Trans Alaska Pipeline System since startup in 1977.
TAPS is owned by a consortium of companies that
include BP Pipelines (Alaska), ConocoPhillips Transportation Alaska,
Inc., ExxonMobil Pipeline Company, Unocal Pipeline Company, and Koch
Alaska Pipeline Company, L.L.C.
More information
about Alyeska’s Strategic Reconfiguration project is available at
www.alyeska-pipe.com.
-30-
|