
ALYESKA REPORT
WEEK OF JULY 8, 1998
|
Pipeline Shutdown Successful
The southern end of the
pipeline was shut down for approximately 14 hours at 6:00 a.m. on Saturday, June 20, for
scheduled maintenance. One pint of oil was spilled near Pump Station 11 during a drain
down process. It was immediately cleaned up. During the shutdown, no safety issues were
identified.
The purpose of the
shutdown was to conduct tests on mainline valves to determine internal seal integrity.
Additional maintenance work was performed at several pump stations and on the Valdez
Marine Terminal. Thirty-eight valves were tested. Early results indicate that 34 valves
sealed and four need further analysis. These tests are part of a four-year comprehensive
valve testing and assessment program to test each of the 177 mainline valves in the
pipeline system. The pipeline was restarted at 7:30 p.m.
This is an
integral part of our long-life strategy to meet the transportation needs for crude oil
into the next century, stated Lee Jones, Senior Vice President for the Fairbanks
Business Unit.
Program valve testing
began last summer when 38 valves were tested. Two valves did not meet Alyeskas
standards. These valves will be replaced or repaired during a major shutdown of the
pipeline scheduled for late September.
North Slope producers
were asked to reduce their flow to 40 percent of their normal production to Pump Station
1. During the maintenance shutdown, Pump Stations 1 through 4 continued to operate at the
reduced flow rate. Relief tanks were used at Pump Stations 1,3 and 5 during the shutdown.
No one was hurt while
performing work during the pipeline shutdown.
|