|
 |
 |
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
|
|
 |
|

ALYESKA REPORT
WEEK OF AUGUST 3, 1998
|
Alyeska Repairs Tanker Vapor
Control Valve
Crews at the Valdez
Marine Terminal are rebuilding a vapor control valve which did not pass a quarterly
preventative maintenance test. The Fenwal valve is part of the Berth 5 tanker
vapor control system. The berth was immediately taken out of service and will remain out
of service until the valve is repaired. As part of the quarterly preventative maintenance
procedure, the valve was operated and did not close when test pressure was applied. The
cause of the problem is corrosion around the O-ring seals. The corrosion appears to be the
result of an extinguishing agent which was released into the system on March 30. A
complete investigation of the corrosion is underway. The valve gate is being thoroughly
cleaned before it is reassembled. During the same preventative maintenance procedure, it
was discovered that several of the pressure sensors and infared detectors in the system
were out of calibration or were otherwise not operating properly. As a result, the
preventative maintenance frequency for the Fenwal system is being reviewed. In the
interim, the Fenwal valve and associated components are being tested prior to each use of
the vapor control system. The Fenwal valves are strategically installed for each berth. If
the sensors detect a flame (through infrared detectors) or a pressure wave, the valve
closes within 50 milliseconds. Twelve high pressure fire extinguishers, six on each side
of the valve, also instantly discharge dry chemical extinguishing agent into the vapor
recovery piping in conjunction with the valve closing. Crude loading operations are
automatically shutdown, and the vapor recovery system is isolated from all other systems.
The Fenwal valve system is one of several safety systems within the Vapor Control process.
A vapor control system shutdown can be initiated by any of the following conditions: high
oxygen content in the vapor suction line; low pressure in the vapor suction line; oxygen
analyzer malfunction; ship vapor compressor shutdown; detonation controller malfunction;
activation of any pipeline detonation detector or failure of detonation system controller;
or by an operator in the Operations Control Center or at the Berth. Taking Berth 5 out of
service will have minimal impact on tanker loading schedules though some uncontrolled
tanker loading is occurring until the valve is repaired. Berth 4, the other berth with
Vapor Controls, was tested and found to be fully functional. Berth 4 continues to crude
loading operations.
Mainline
Valve Develops Minor Weep
A pipeline check
valve south of Thompson Pass has developed a minor weep near the top of the valve. Sorbent
pads have been placed around the weep to collect any oil. No oil has been released to the
ground. The weep is occurring at about a rate of one drop every 24-hours. The valve was
excavated about six weeks ago in preparation for repair work on the valve scheduled for
late September. It is believed that the removal of the soil from on top of the valve
relaxed the O-ring, allowing the seep to begin. The weep will be monitored and repaired as
part work to be performed in September.
Tanker
Escort System Begins Transition to Single Vessel Contractor
Alyeska Pipelines Ship Escort
Response Vessel System (SERVS) began the transition to a single vessel contractor on
August 1, 1998. Crowley Marine Services will become Alyeskas vessel contractor
following a two year transition period. These vessels are used as part of the tanker
escorts and for oil spill prevention and response in Prince William Sound. Alyeska moved
to a single contractor to provide the most efficient use of the vessels in Prince William
Sound.
Tidewater vessels have served as escort
tugs and escort vessels for the past nine years. The Tidewater vessels will be phased out
of service and replaced by Crowley vessels over the next two years. Two Tidewater tugs and
an escort response vessel were released from service on August 1 and two Crowley tractor
tugs, The Protector and The Guard, joined the SERVS fleet in their place.
Mainline Valve
Repair Presentation
Alyeska Pipeline will hold an
informational presentation in Fairbanks on the Mainline Valve Replacement and Repair
Projects scheduled for later this summer. As part of these projects, one valve will be
replaced and another repaired in place to bring the valves up to Alyeskas
operational standards. The presentation will be held Thursday, August 6 from 7:30 a.m. to
10:30 a.m. at the Doyon Industrial Facility, followed by a tour of Pump Station 9 near
Delta. If media are interested in joining the presentation and/or the tour of Pump Station
9, please contact Jennifer Ruys.
Pipeline
Reliability Remains Above 99%
| July Reliability |
100.00% |
| 1998 Reliability |
99.80% |
| July Throughput |
36,608,222 barrels |
| July Daily Average Throughput |
1,180,910 barrels per day |
| 1998 Throughput |
259,578,812 barrels |
| 1998 Daily Average |
1,224,428 barrels per day |
|
 |