
ALYESKA REPORT
WEEK OF MAY 5, 1999
|
Alyeska Installs Structural
Sleeves
Alyeska Pipeline has installed two 4-foot
steel bands (sleeves) on the outside of the pipeline to reinforce two areas of pipe
impacted by corrosion. The corrosion is near pipeline welds and was detected by
instrumented pigs sent through the pipeline to check for external corrosion.
Some pipe settlement had occurred in the area causing the insulating jacket around the
pipe to crack. This allowed water to seep underneath the protective tape around the welds.
The sleeves completely encircle the pipe to reinforce pipe strength. Alyeska has been
monitoring this section of pipe for approximately four years. Data indicated that
corrosion in this area had increased and the location was put on the list of sites to be
inspected.
The sleeves were installed at pipeline Mile
Post 652, near Sourdough along the Richardson Highway. Mile Post 652 is a specially buried
and refrigerated section where the pipeline dips below ground to allow animals to cross
the pipeline right of way.
This site is the next to the last to be
excavated of the 10 that were identified for inspection this year. Of the nine inspected,
only the MP652 location needed major maintenance and repair work. The other eight
locations required minor maintenance which included recoating the pipe.
These ten areas were selected from the data
received from the instrumented pigs that were run through pipeline last year. This special
instrumentation pig ultrasonically tests the wall thickness of the pipe to determine if
corrosion is present. After analyzing the data, certain areas are identified each year for
excavation and inspection.
The corrosion inspections began in February
and are expected to continue through August. Some 30 workers will complete the $4.5
million project.
Summer Tank Maintenance Begins
Alyeska Pipeline took one of the crude
storage tanks at the Valdez Marine Terminal out of service last week for maintenance. The
500,000 barrel tank will be drained, cleaned, inspected and re-coated before being
returned to service. A second storage tank is being prepared to be taken out of service
for maintenance as well.
The crude storage tanks along the Trans
Alaska Pipeline System must be inspected every 5 to 10 years. There are 18 crude storage
tanks at the Valdez Marine Terminal.
The two crude tanks will have new bottoms
and Cathodic Protection Systems installed. A third tank in the Ballast Water Treatment
System will be cleaned, inspected, repaired, re-coated internally and re-serviced this
summer as well.
If you would
like a tour of this project, please contact Tracy Green, 787-8679.
Pipeline
Reliability
Pipeline throughput for April 1999 totaled
32,461,000 barrels, with a daily average of 1.08 million barrels per day. Pipeline
throughput for the year to date is 137,999,000 barrels, averaging 1.15 million barrels per
day. Pipeline reliability for April was 99.80 percent, making the year to date reliability
99.86 percent.
Back to top
|