
ALYESKA REPORT
WEEK OF JUNE 14, 1999
|
Pump Station 9 Returns to Normal
Operation
Pump Station 9 returned to normal operation
today after modifying its operation to prepare for approach of the Donnelly Flats wildland
fire. The pipeline Right Of Way was inspected today and all pipeline facilities in the
area are safe.
The fire approached the pump station
perimeter yesterday. One small fire occurred inside the pump stations fenced area
yesterday when a wooden pallet caught fire. The pump station crew extinguished the fire
using the station fire truck. Alyeska crews will continue to patrol and monitor inside the
station fencing for the next few days.
To prepare for the possibility of the fire
near the station, Alyeska crews cleared brush away from the perimeter of the station;
built a reflective shelter around Block Valve 2; added sprinklers to the tank farm, Block
Valve 2 and the office building; and moved all equipment away from the fence to limit fire
access to fuel sources. The station also filled its crude relief tank to almost full to
limit the volume of crude vapors in the tank and to provide thermal balancing.
Work Resumes on Valve Upgrade
Project
Crews returned to work on a project to
upgrade the control systems for the Remote Gate Valves on the afternoon of June 8 after
almost eight months. The project was shutdown in October by Sr. Vice President Bill Howitt
because of inefficient management of the project, inadequate implementation of
Alyeskas Quality Program and the allegations of a hostile work environment on the
project. A list of items to correct the deficiencies had to be completed before work on
the project was allowed to resume. On Wednesday, June 8, 1999, that permission was granted
by Howitt in Fairbanks.
To resume work, the project team had to
develop a restart plan that would address the project management issues and the use of
Alyeskas Quality Program. A separate assessment of the project, including the open
workplace issues was conducted. Each of the nine findings from the assessment was
addressed by the project team. Some of the remedial actions taken prior to restart of the
project include clarification of the roles and responsibilities of the project team; clear
guidance on how to address out of scope issues; and a clarification of the
electrical codes to be used for work and inspection.
Im very pleased with the work
done to restart on the project, said Howitt. The project team developed a
clear mission, clear roles and responsibilities and a clear scope of work. Overall,
theyve taken control of the project and developed it into a project that meets my
expectations of Operational Excellence.
Back to top
|